Reduction of Extensive Construction Costs & Lead Times of Single-Family Homes in Florida due to Covid-19
dc.contributor.advisor | Cruzado Vélez, Héctor J. | |
dc.contributor.author | Camara, Otavio | |
dc.date.accessioned | 2024-03-06T17:03:26Z | |
dc.date.available | 2024-03-06T17:03:26Z | |
dc.date.issued | 2022 | |
dc.description | Design Project Article for the Graduate Programs at Polytechnic University of Puerto Rico | en_US |
dc.description.abstract | The timely completion of single-family homes in Florida was significantly affected by the outbreak of COVID-19 due to increased prices of materials, services, and lead time. Supply chain disruption and inefficient project management processes emerged as the main causes for increased costs and delays, leading to low profitability projects and businesses bankruptcies. In this study, data was collected from vendors and builders in Orlando, FL before and after the pandemic in an effort to optimize the project management process and consequently reduce the long lead-times and cost of construction. It was found that by creating a comprehensive construction schedule, using project management software to streamline their supply chain, embracing strategic procurement techniques, and value-adding supply chain management, an effective and profitable deliver of single-family homes is possible. Key Terms ⎯ construction materials and services, construction costs, Covid-19, lead time. | en_US |
dc.identifier.citation | Camara, O. (2022). Reduction of Extensive Construction Costs & Lead Times of Single-Family Homes in Florida due to Covid-19 [Unpublished manuscript]. Graduate School, Polytechnic University of Puerto Rico. | en_US |
dc.identifier.uri | http://hdl.handle.net/20.500.12475/2235 | |
dc.language.iso | en | en_US |
dc.publisher | Polytechnic University of Puerto Rico | en_US |
dc.relation.haspart | San Juan | en_US |
dc.relation.ispartof | Management; | |
dc.relation.ispartofseries | Fall-2022; | |
dc.rights.holder | Polytechnic University of Puerto Rico, Graduate School | en_US |
dc.rights.license | All rights reserved | en_US |
dc.subject.lcsh | Polytechnic University of Puerto Rico--Graduate students--Research | en_US |
dc.subject.lcsh | Polytechnic University of Puerto Rico--Subject headings--Unassigned | en_US |
dc.subject.lcsh | Polytechnic University of Puerto Rico--Graduate students--Posters | en_US |
dc.subject.lcsh | Polytechnic University of Puerto Rico--Graduate School--Master in Engineering Management degree | en_US |
dc.title | Reduction of Extensive Construction Costs & Lead Times of Single-Family Homes in Florida due to Covid-19 | en_US |
dc.type | Article | en_US |
Files
Original bundle
1 - 2 of 2
Loading...
- Name:
- PUPR_CEAH_SJU_FA22_MEM_Otavio Camara_Article.pdf
- Size:
- 333.45 KB
- Format:
- Adobe Portable Document Format
- Description:
- PUPR_CEAH_SJU_FA22_MEM_Otavio Camara_Article
Loading...
- Name:
- PUPR_CEAH_SJU_FA22_MEM_Otavio Camara_Poster.pdf
- Size:
- 368.19 KB
- Format:
- Adobe Portable Document Format
- Description:
- PUPR_CEAH_SJU_FA22_MEM_Otavio Camara_Poster
License bundle
1 - 1 of 1
Loading...
- Name:
- license.txt
- Size:
- 1.63 KB
- Format:
- Item-specific license agreed upon to submission
- Description: